Baxter's $58 Million Highway 371 Overpass: What to Know

Baxter's biggest traffic project is moving forward: a $58 million overpass that lifts Highway 371 over the railroad and Highway 210. Here is the timeline and what it changes.

Noah Goedker

Noah Goedker

Elevate Group · eXp Realty

An aerial view of a large highway interchange under construction with an elevated bridge crossing railroad tracks and a roundabout taking shape below
PLATE 01 — An aerial view of a large highway interchange under construction with an elevated bridge crossing railroad tracks and a roundabout taking shape below

The biggest infrastructure project in Baxter's recent history is officially on the books. MnDOT's $58 million grade-separated overpass will lift Highway 371 over the BNSF railroad tracks and Highway 210 near the Highway 210 and 371 interchange, replacing the at-grade crossing where trains and signalized traffic have slowed drivers for years. MnDOT greenlit the project in February 2026 after the Baxter City Council granted municipal consent, and construction is now scheduled for 2028 and 2029.

Why Is the Crossing Being Rebuilt?

When a train rolls through the Highway 210 and 371 junction, traffic stacks up. The overpass removes that friction by carrying Highway 371 over the tracks and over Highway 210 on a raised structure, with a second bridge over Excelsior Road. The design is called a buttonhook because traffic leaves the main line, circles around, and rejoins, which is how the interchange keeps every movement open without a stop.

What Drivers Should Expect

The project adds five roundabouts, two on Highway 210 and the others on either side of Highway 371. Traffic on 371 rises onto the overpass at speed, merges right, and circles the roundabouts to reach businesses along the corridor, including the grocery anchors. Missed exits mean about a mile of backtracking, and the retaining walls will change how some businesses are reached, which is exactly why the council attached conditions before consenting.

The Timeline

  • Municipal consent: the Baxter City Council voted 3 to 2 on January 20, 2026 to support the project, contingent on seven conditions.
  • Green light: MnDOT approved the project in February 2026 after the conditions were met.
  • Design: final design runs from March 2026 through July 2027, with contractor selection expected in November 2027.
  • Construction: the build is slated for 2028 and 2029.
  • What It Means for Buyers

    A town that clears a railroad bottleneck is a town planning for more people. Baxter is already the commercial center of the lakes area, and an overpass that keeps 371 moving supports both daily commutes and the weekend lake traffic. It fits the same pattern as the growth along the corridor and the development pipeline the city is working through. Our Highway 371 growth story and the development roundup give the full context, and the Baxter community guide covers daily life.

    Questions about how the project could affect your search? Schedule a call and we can talk it through. Cheers!

    Have Questions About Lake Property?

    We help buyers and sellers navigate lake-home decisions with clarity and local expertise. Let's talk about your situation.